REQUEST FOR PROPOSAL (RFP)
Construction Contractor for RW-3 Infrastructure Project
RFP Reference: ZRW-USG-2RW3-2026
Date Issued: 18th March 2026
Submission Deadline: 3rd April 2026
1. Introduction
Zipline Rwanda Ltd invites qualified civil works contractors to submit technical proposals for
prequalification for the RW-3 infrastructure construction project to be located at Gatwaro Village, Kibuye Cell, Kwishyura Sector, Karongi District, Western Province.
The purpose of this Request for Technical Proposals (RTP) is to identify and shortlist capable
contractors with the technical, financial, and operational capacity to deliver the RW-3 project.
At the time of issuing this RTP, final construction designs and Bills of Quantities (BoQ) are still under development. Therefore, financial proposals are not required at this stage.
Only shortlisted contractors will be invited to participate in the second stage of the procurement process, where final designs will be issued and financial proposals will be requested.
1.1 Procurement Process
Zipline will implement a two-stage contractor selection process.
Stage 1 – Contractor Prequalification
Contractors submit:
Based on evaluation, Zipline will shortlist a limited number of contractors (typically 3–5).
Stage 2 – Financial Tender (Shortlisted Contractors Only)
Shortlisted contractors will receive:
Shortlisted contractors will then submit:
The contract will be awarded based on combined technical and financial evaluation.
2. Project Overview
The RW-3 project supports Zipline’s logistics and drone delivery operations.
Construction activities may include:
All works shall follow approved engineering designs and technical specifications. Final designs and construction specifications will be provided during Stage 2 of the procurement process.
3. Scope of Work
The contractor will be responsible for executing all works required to deliver the RW-3 infrastructure facility.
3.1 Site Mobilization and Preparation
The contractor shall:
3.2 Civil and Structural Works
The contractor shall perform:
3.3 Mechanical, Electrical and Plumbing (MEP) Works
The contractor shall install:
3.4 External Works
External works may include:
3.5 Prefabricated Structure Installation
The contractor will support the unloading and installation of prefabricated structures delivered to the site.
Expected installation duration: 20 days, depending on site conditions and logistical arrangements.
3.6 Tent Installation
Operational tents required for Zipline operations will be assembled and installed by the contractor in coordination with Zipline supervisors.
Expected installation duration: approximately 5 days.
3.7 Drone Recovery and Launcher Installation Support
The contractor will assist with preparation of bases and anchoring systems required for the drone recovery and launcher infrastructure.
Specialized equipment such as a hydraulic stake rammer may be used for installing recovery system base plates where required.
This equipment may be rented temporarily for installation activities.
3.8 Testing, Commissioning and Handover
The contractor shall:
4. Contractor Qualification Requirements
4.1 Experience in Similar Works
The bidder must have:
certificate signed by the client.
5. Equipment and Machinery Requirements
The contractor must demonstrate access to the following essential equipment:
Additional specialized equipment (if required):
Bidders must provide proof of ownership or valid leasing agreements covering the contract period.
6. Personnel Requirements
The bidder must demonstrate the availability of qualified personnel for the following positions.
Project Manager
Civil Site Engineer
Electrical Engineer
Quantity Surveyor
Environmental and Social Safeguards Expert
Site Foreman
Plumbing Technician
Electrical Technician
Language Requirement
All engineers, foremen, and technicians must be able to communicate in English to coordinate
effectively with Zipline installation supervisors responsible for prefabricated structures and tent installations.
7. Financial and Administrative Requirements
Bidders must submit:
Average annual turnover must be at least RWF 400,000,000.
8. Required Proposal Documents
The technical proposal must include:
Company Profile
Relevant Project Experience
Construction Methodology
Equipment Availability
Personnel
Other Supporting Documents
9. Evaluation Criteria
Proposals will be evaluated using the following criteria:
Criteria Weight
Relevant construction experience 30%
Key personnel qualifications 25%
Equipment and technical capacity 15%
Construction methodology 15%
Financial capacity 10%
HSE approach 5%
Only bidders scoring 70% or higher in the technical evaluation will proceed to financial evaluation.
10. Submission Guidelines
All proposals must be submitted electronically in PDF format to:
Subject line:
RFP – RW-3 Civil Works Contractor
Submission Deadline: 3rd April 2026
Late submissions will not be accepted.
11. Clarifications
All clarification requests must be submitted in writing to provided emails on section 10
Clarification deadline: 27th March 2026
Responses may be shared with all bidders.
12. Confidentiality
All information contained in this RFP shall be treated as confidential and used solely for the purpose of preparing proposals.
13. Zipline Rights
Zipline Rwanda Ltd reserves the right to:
Attachment
Join a Focused Community on job search to uncover both advertised and non-advertised jobs that you may not be aware of. A jobs WhatsApp Group Community can ensure that you know the opportunities happening around you and a jobs Facebook Group Community provides an opportunity to discuss with employers who need to fill urgent position. Click the links to join. You can view previously sent Email Alerts here incase you missed them and Subscribe so that you never miss out.